Shamlaji to Mota Chiloda

6-laning of Shamlaji to Mota Chiloda (from Ch. 401+200 to Ch. 494+410) section of NH 8 in the state of Gujarat on Hybrid Annuity Mode.

Salient Features :

Length of road – 93.21 km
Railway Over Bridge (ROB) – 4 Nos.
Vehicular Underpass (VUP) – 8 Nos.
Light vehicular underpass (LVUP) – 12 Nos.
Minor Bridge – 10 Nos.
Flyover – 9 Nos.
Culverts – 130 Nos.
Toll plaza – 2 Nos.

Services provided :

Survey & investigations
Detail design of Highway and structures
Design of toll plaza and way side amenities

TEAM ASSIGNED :

Apurva Parikh – Team Leader
Varshil Parikh – Sr. Highway Engineer
Dhrumil Parikh – Sr. Bridge Engineer
Darshit Shah – Highway design Engineer
Nisarg Shah – Bridge design Engineer
Vaibhav Doshi – Bridge design Engineer

Widening from 4 –lane to 6 – Lane of Shamlaji to Mota Chiloda (NH-8)
Client Name

National Highways Authority of India

Estimated Cost

Rs. 1150 Cr.